No Name Project Approved!

The MOA has been finalized and the USFS just signed the Decision Notice.  This now officially approves the No Name Basin terrain expansion project to move forward!  This project will add 377 acres to our existing Special Use permit along with ten cut trails, additional gladed terrain, a fixed-grip triple carrier lift, a warming house, and restrooms at the bottom terminal.  Official work will now begin on this project.  We are SO excited to actually get started on this project after years of planning and project review by multiple entities.  This project will involve two summers of construction (2024 & 2025) with the No Name Basin terrain scheduled to open for the 2025-26 winter season.  Stay tuned for details on this project as they unfold.